Report_Id:   229903   Est NO  0006

Date:12/29/2022

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 229903 Estimate Number 0006 Estimate Type PROGRESS
District Office PIKEVILLE (12360)  Wright, Doug

Contractor M & M SERVICES CO INC ADDR SN 0 VC Code KY0036144
229 MIDLAND TR
MT STERLING , KY , 40353
Pay Period 11/19/2022  TO  12/02/2022
Date Approved 12/07/2022
Primary Proj Number BR06017702200
Project No. EMERGENCY
Primary County KNOTT
Name of Road EDWARD DRIVE OVER TROUBLESOME CREEK
Description DR-4663-KY. REPLACE BRIDGE (060C00093N) ON EDWARD DRIVE OVER TROUBLESOME CREEK.
     
     
Date Let 08/01/2022 Formal Acceptance
Date Awarded 08/01/2022 Date Work Began 08/09/2022
Date Contract Executed 08/01/2022 Open To Traffic
Date NTP Issued 08/01/2022 Actual Completion Date 11/18/2022

Current Contract Amount

$550,849.95

Total to Date

Prev to Date

This Estimate

Original Amount

$550,849.95

Total Earnings

$457,916.93

$419,116.90

$38,800.03

Percent Complete

83.13

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$92,933.02

Gross Earnings

$457,916.93

$419,116.90

$38,800.03

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$457,916.93

$419,116.90

$38,800.03

Contract Id 229903

Change Order Summary

County KNOTT
Estimate Nbr 0006 Project Number EMERGENCY
Contractor M & M SERVICES CO INC Period 11/19/2022  TO  12/02/2022
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 229903

COMMONWEALTH OF KENTUCKY

County KNOTT
Contract Type BRRL   BRIDGE REPLACEMENT

TRANSPORTATION CABINET

Primary Project Number BR06017702200
Estimate Nbr 0006 Period 11/19/2022  TO  12/02/2022
Contractor M & M SERVICES CO INC
 
Project BR06017702200 Fed/State Project Number EMERGENCY Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project BR06017702200 Fed/State Project Number EMERGENCY Category 0001 BRIDGE - 060C00093N
0005 DGA BASE 00001 TON 156.00 156.000 181.820 181.820 135.00 24,545.70
0010 GRANULAR EMBANKMENT 02223 CUYD 663.00 663.000 161.958 347.980 509.938 85.00 13,766.43 43,344.73
0015 STRUCTURE GRANULAR BACKFILL 02231 CUYD 130.00 130.000 95.953 95.953 115.00 11,034.59
0020 TEMPORARY SIGNS 02562 SQFT 64.00 64.000 54.000 54.000 25.00 1,350.00
0025 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 15,000.00 15,000.00
0030 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 0.000 0.000 1,800.00 0.00
0035 STAKING 02726 LS 1.00 1.000 1.000 1.000 11,500.00 11,500.00
0040 ARMORED EDGE FOR CONCRETE 03299 LF 30.00 30.000 30.000 0.000 30.000 180.00 5,400.00 5,400.00
0045 STRUCTURE EXCAVATION-COMMON 08001 CUYD 220.00 220.000 245.420 0.000 245.420 80.00 19,633.60 19,633.60
0050 FOUNDATION PREPARATION 08003 LS 1.00 1.000 1.000 1.000 22,000.00 22,000.00
0055 CYCLOPEAN STONE RIP RAP 08019 TON 570.00 570.000 363.880 363.880 120.00 43,665.60
0060 PILES-STEEL HP12X53 08046 LF 110.00 110.000 146.420 146.420 155.00 22,695.10
0065 PILE POINTS-12 IN 08094 EACH 8.00 8.000 8.000 8.000 150.00 1,200.00
0070 CONCRETE-CLASS A 08100 CUYD 34.00 34.000 21.100 21.100 825.00 17,407.50
0075 CONCRETE-CLASS AA 08104 CUYD 31.00 31.000 39.190 39.190 1,650.00 64,663.50
0080 STEEL REINFORCEMENT-EPOXY COATED 08151 LB 6,800.00 6,800.000 6,713.380 6,713.380 2.35 15,776.44
0085 GRANULAR PILE CORE 20209EP69 CUYD 110.00 110.000 0.000 0.000 100.00 0.00
0090 EROSION CONTROL 21415ND LS 1.00 1.000 1.000 1.000 8,500.00 8,500.00
0095 EMBANKMENT 21553EN CUYD 1,259.00 1,259.000 575.370 575.370 65.00 37,399.05
0100 TRANSPORT AND SET CONCRETE BEAMS 4 BOX BEAMS 22894NN LS 1.00 1.000 1.000 1.000 65,000.00 65,000.00
Project BR06017702200 Fed/State Project Number EMERGENCY Category 0003 DEMOBILIZATION
0105 MOBILIZATION 02568 LS 1.00 1.000 1.000 1.000 25,861.50 25,861.50
0110 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.250 7,758.45 1,939.61

SUBTOT

$38,800.03

$457,916.93

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00